File #: 7031   
Type: Consent Status: Passed
File created: 11/3/2022 Department: Public Works-Transportation
On agenda: 11/15/2022 Final action: 11/15/2022
Subject: California Environmental Quality Act Finding for the Fontana Avenue and Valley Boulevard Project in the Fontana Area
Attachments: 1. MAP-PW-Trans 11-15-22 CEQA for Fontana Avenue and Valley Boulevard Project, Fontana Area, 2. ATT-PW-Trans 11-15-22 CEQA for Fontana Avenue and Valley Boulevard Project, Fontana Area - NOE, 3. Item #61 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

November 15, 2022

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
California Environmental Quality Act Finding for the Fontana Avenue and Valley Boulevard Project in the Fontana Area
End

RECOMMENDATION(S)
Recommendation
1. Find that the Fontana Avenue and Valley Boulevard Project in the Fontana area is exempt under the California Environmental Quality Act Guidelines, Title 14 of the California Code of Regulations Section 15301(c) Class 1 (existing facilities) and Section 15302(c) Class 2 (replacement or reconstruction).
2. Approve the Fontana Avenue and Valley Boulevard Project in the Fontana area as defined in the Notice of Exemption and direct the Clerk of the Board of Supervisors to file and post the Notice of Exemption.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Fontana Avenue and Valley Boulevard Project in the Fontana area (Project) will be funded with Gas Tax funds and Senate Bill 1 (SB1) Road Maintenance and Rehabilitation Account (RMRA) funds. The requested actions are administrative in nature with minimal financial impact. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2022-23 Road Operations budget (66500002000 34H15064) and will be included in future recommended budgets.

BACKGROUND INFORMATION
The Project involves approximately three miles of pavement rehabilitation on Fontana Avenue and Valley Boulevard, repairing sidewalks at various locations, updating existing curb ramps in accordance with current design standards and purs...

Click here for full text