San Bernardino header
File #: 7319   
Type: Consent Status: Passed
File created: 12/28/2022 Department: Real Estate Services
On agenda: 1/10/2023 Final action: 1/10/2023
Subject: Amendment to Lease Agreement with Upland Unified School District for Classroom Space, Office Space, and Playground Area in Upland
Attachments: 1. CON-RESD-PSD-011023-Lease Amd w Upland Unified School District 00-802 A9, 2. Item #41 Executed BAI, 3. 00-891-A-9 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

January 10, 2023

 

FROM

TERRY W. THOMPSON, Director, Real Estate Services Department

JACQUELYN GREENE, Director, Preschool Services Department 

         

SUBJECT                      

Title                     

Amendment to Lease Agreement with Upland Unified School District for Classroom Space, Office Space, and Playground Area in Upland

End

 

RECOMMENDATION(S)

Recommendation

Approve Amendment No. 9 to Lease Agreement No. 00-802 with Upland Unified School District to extend the term of the lease two years for the period of February 1, 2023 through January 31, 2025, following a permitted month-to-month holdover from August 1, 2020 through January 31, 2023, and adjust the rental rate schedule for approximately 3,840 square feet of classroom and office space, 6,000 square feet of parking lot area, and 3,200 square feet of playground area located at 732 North 3rd Avenue in Upland for the Preschool Services Department in the amount of $161,730.

(Presenter: Terry W. Thompson, Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Operate in a Fiscally-Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost) as the program is 86% federally funded and 14% state funded.  The total cost of this two-year extension, including the permitted month-to-month holdover period, is $161,730.  Lease payments will be made from the Real Estate Services Department (RESD) Rents budget (7810001000) and reimbursed from the Preschool Services Department (PSD) budget (5911622220).  Other costs associated with this lease include custodial, minor interior maintenance, routine maintenance of the grounds, landscaping, parking area, and playground, utility expenses, and telephone expenses, which will be paid from the PSD budget.  Sufficient appropriation is included in the 2022-23 PSD and Rents budgets and will be included in future recommended budgets.  Annual lease costs are as follows:

 

 Year

Annual Lease Cost

Estimate of Other Costs Associated With This Lease

August 1, 2020 - January 31, 2023

$  89,850

$43,176

February 1, 2023 - January 31, 2024

$  35,940

$14,823

February 1, 2024 - January 31, 2025

$  35,940

$15,268

Total Cost

$161,730

$73,267

 

BACKGROUND INFORMATION

The recommend action will amend an existing lease agreement with Upland Unified School District to extend the term of the lease for two years for the period of February 1, 2023 through January 31, 2025, following a permitted month-to-month holdover from August 1, 2020 through January 31, 2023, and adjust the rental rate schedule for the use of approximately 3,840 square feet of classroom and office space, 6,000 square feet of parking lot area, and 3,200 square feet of playground area located at 732 North 3rd Avenue in Upland because of the continuing need to provide PSD services in the Upland area. 

PSD has occupied the preschool facility located at 732 North 3rd Avenue in Upland since 1997 under the provisions of Lease Agreement No. S98-014, which was originally approved by the Director of RESD and subsequently converted to Lease Agreement No. 00-802.  In the 25 years since the lease was originally approved, RESD and the Board of Supervisors (Board) have approved eight amendments to extend the term of the lease through July 31, 2020, increase the parking lot area from 3,000 square feet to 6,000 square feet, and update standard lease agreement language.

 

Amendment No.

Approval Date

Item No.

1

March 30, 1999

N/A

2

July 11, 2000

48

3

June 3, 2003

72

4

August 17, 2004

48

5

June 5, 2007

63

6

July 13, 2010

60

7

June 25, 2013

84

8

July 25, 2017

37

 

On October 3, 2022, PSD notified RESD of its desire to extend the term of Lease Agreement No. 00-802 and requested that RESD process Amendment No. 9 for the extension and negotiate the rental rate for the extended term of the lease.  RESD conducted a market survey and determined that the lease rate at the time of renewal was below the market rate.

 

During negotiations regarding the rental rate for the extension of Lease Agreement No. 00-802, the lease went into hold over status as of August 1, 2020.  PSD continued to occupy the premises and abide by the provisions of the lease on a month-to-month basis while it was decided whether to remain in this location.  Amendment No. 9 to Lease Agreement No. 00-802 provides for PSD’s continued use of approximately 3,840 square feet of classroom and office space, 6,000 square feet of parking lot area, and 3,200 square feet of playground area located at 732 North 3rd Avenue in Upland for the period of February 1, 2023 through January 31, 2025, following a permitted holdover period from August 1, 2020 through January 31, 2023.  All other terms and conditions of Lease Agreement No. 00-802 remain unchanged.

 

Staff has reviewed the recommended action pursuant to the California Environmental Quality Act (CEQA) and has determined that it does not constitute a project.  Accordingly, no further action, is required under CEQA.

 

Summary of Lease Terms

 

Lessor:

Upland Unified School District  (Terry Comnick, Assistant Superintendent of Business)

 

 

Location:

732 North 3rd Avenue, Upland

 

 

Size:

3,840 square feet of classroom/office space, 6,000 square feet of parking lot area and 3,200 square feet of playground area

 

 

Term:

Two years commencing February 1, 2023

 

 

Options:

Two three-year extension options remain

 

 

Rent:

Cost per square foot per month (classroom and office space):  $.78*

 

Monthly:  $2,995

 

Annual:  $35,940

 

*Below-range for comparable facilities in the Upland area per supporting lease comparable on file with RESD

 

 

Annual Increases:

None

 

 

Improvement Costs:

None

 

 

Custodial:

To be provided by County

 

 

Maintenance:

To be provided by Lessor except County provides minor interior maintenance, routine maintenance of the grounds, landscaping, parking area, and playground

 

 

Utilities:

County pays 10% of all utility costs 

 

 

Insurance:

The Certificate of Liability Insurance, as required by the lease, is on file with RESD

 

 

Right to Terminate:

County has the right to terminate with 90-days’ notice

 

 

Parking:

Sufficient for County needs

 

PROCUREMENT

The procurement process required by County Policy 12-02 - Leasing Privately-Owned Real Property for County Use does not apply to leases of real property owned by a federal agency, the State, a city, a county, a school district, special district, or other public entity.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Agnes Cheng, Deputy County Counsel, and Adam Ebright, Deputy County Counsel, 387-5455) on November 14, 2022; Preschool Services (Jacquelyn Greene, Director, 383-2078) on December 1, 2022; Purchasing (Bruce Cole,

 

 

 

 

Supervising Buyer, 387-2148) on December 7, 2022; Finance (Paul Garcia, Administrative Analyst, 385-8392, and Penelope Chang, Administrative Analyst, 387-4886) on December 12, 2022; and County Finance and Administration (Valerie Clay, Deputy Executive Officer, 387-5423) on December 15, 2022.

 

(AR: 893-0002)