San Bernardino header
File #: 7322   
Type: Consent Status: Passed
File created: 12/28/2022 Department: Public Works-Transportation
On agenda: 1/10/2023 Final action: 1/10/2023
Subject: California Environmental Quality Act Finding for the Park Drive and Other Roads Project in the Wrightwood Area
Attachments: 1. ATT-PW-Trans 1-10-23 CEQA for Park Drive and Other Roads Project, Wrightwood Area - NOE, 2. MAP-PW-Trans 1-10-23 CEQA for Park Drive and Other Roads Project, Wrightwood Area, 3. Item #37 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

January 10, 2023

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
California Environmental Quality Act Finding for the Park Drive and Other Roads Project in the Wrightwood Area
End

RECOMMENDATION(S)
Recommendation
1. Find that the Park Drive and Other Roads Project in the Wrightwood Area is exempt under the California Environmental Quality Act Guidelines, Title 14 of the California Code of Regulations Section 15301(c) Class 1 (existing facilities) and Section 15302(c) Class 2 (replacement or reconstruction).
2. Approve the Park Drive and Other Roads Project in the Wrightwood Area as defined in the Notice of Exemption and direct the Clerk of the Board of Supervisors to file and post the Notice of Exemption.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Park Drive and Other Roads Project in the Wrightwood Area (Project) will be funded with Senate Bill 1 (SB1) Road Maintenance and Rehabilitation Account (RMRA) funds. The requested actions are administrative in nature with minimal financial impact. The estimated cost to secure environmental compliance for this Project is $2,600 and sufficient appropriation and revenue are included in the Department of Public Works (Department) 2022-23 Road Operations budget (66500002000 34H15113) and will be included in future recommended budgets.

BACKGROUND INFORMATION
The Project involves approximately 0.35 miles of pavement rehabilitation on Apple Avenue and Evergreen Road, pavement rehabilitation and reconstruction on Park Drive, constructing new curb ramps i...

Click here for full text