Subject: Request for Qualifications for County Government Center Parking Structure Design-Build Project
Attachments: 1. ATT-PFMD-012423-Request for Qualification-CGC Parking Structure-1379, 2. Item #36 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

January 24, 2023

FROM
DON DAY, Director, Project and Facilities Management Department

SUBJECT
Title
Request for Qualifications for County Government Center Parking Structure Design-Build Project
End

RECOMMENDATION(S)
Recommendation
1. Authorize the Director of the Project and Facilities Management Department to utilize the Design-Build Project delivery method pursuant to Public Contract Code Section 22160 et seq. for the delivery of the County Government Center Parking Structure Design Build Project.
2. Approve the Design-Build Request for Qualifications Package to establish a short list of Design-Build Entities who will compete to provide design and construction services for the County Government Center Parking Structure Design Build Project.
3. Authorize the Director of the Project and Facilities Management Department to release the Design-Build Request for Qualifications Package.
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.

FINANCIAL IMPACT
Approval of this item will result in the use of additional Discretionary General Funding (Net County Cost). Dependent on the final design and specifications, the total cost of the County Government Center Parking Structure Design Build Project (Project) (WBSE 10.10.1379) is estimated to be between $70 million and $78 million. The Board of Supervisors (Board) approved the allocation of $30 million in Discretionary General Funding towards this project in the 2022-23 Adopted Budget and additional Discretionary General Funding will be included in future recommended budgets, as needed, to fund remaining costs.

BACKGROUND INFORMATION
The Project, located in the City of San Bernardino, will be a multi-level, parking structure comprised of approximately 2...