REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
April 8, 2025
FROM
DON DAY, Director, Project and Facilities Management Department
SHANNON D. DICUS, Sheriff/Coroner/Public Administrator
SUBJECT
Title
Amendment and Change Order to Construction Contract with Angeles Contractor, Inc. for the Sheriff Colorado River Station Remodel Project in Needles
End
RECOMMENDATION(S)
Recommendation
1. Approve Amendment No. 4 to Construction Contract No. 23-929 with Angeles Contractor, Inc., for the Sheriff Colorado River Station Remodel Project in Needles, increasing the contract amount by $281,412, from $10,391,615 to $10,673,027 for the additional scope of work, with no change to the construction contract term of 393 days (Four votes required).
2. Approve Change Order No. 7 to Construction Contract No. 23-929 with Angeles Contractor, Inc., increasing the total amount by $12,032, from $10,673,027 to $10,685,059, for additional scope of work, with no change to the construction contract term of 393 days, for the Sheriff Colorado River Station Remodel Project in Needles (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Sheriff Colorado River Station Remodel Project (Project) (WBSE 10.10.1220) budget of $13,952,484 is funded from Discretionary General Funding ($6,594,490) and Proposition 172 funds ($7,357,994), as part of the 2024-25 Capital Improvement Program (CIP) budget approved by the Board of Supervisors (Board).
BACKGROUND INFORMATION
Approval of Amendment No...