REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION
December 17, 2019
FROM
BRENDON BIGGS, Interim Chief Flood Control Engineer, Flood Control District
SUBJECT
Title
Contract with KEC Engineering for the Santa Ana River Floodwall Remediation Project
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District (District):
1. Approve Addendum No 1, issued on October 24, 2019, and Addendum No. 2, issued November 4, 2019 to the bid documents for the Santa Ana River Floodwall Remediation project (Project) in the Colton area.
2. Award a contract to KEC Engineering (Corona, CA), in the amount of $949,583 for the Project.
3. Authorize a contingency fund of $94,958 for the Project.
4. Authorize the Chief Flood Control Engineer or Interim Chief Flood Control Engineer to approve the expenditure of the contingency fund of $94,958 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Chief Flood Control Engineer or Interim Chief Flood Control Engineer to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $59,979 of the $94,958 contingency fund, pursuant to Public Contract Code section 21061(d).
6. Authorize the Chief Flood Control Engineer or Interim Chief Flood Control Engineer to accept the work when complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Interim Chief Flood Control Engineer, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The District is funded by property taxes, fees, local, state, and fed...
Click here for full text