San Bernardino header
File #: 1440   
Type: Consent Status: Passed
File created: 12/9/2019 Department: Real Estate Services-Project Management Division
On agenda: 12/17/2019 Final action: 12/17/2019
Subject: V Amendment No. 1 to Construction Contract with Abboud Diamond Construction, Inc. for Onyx Peak Solar Upgrade Project
Attachments: 1. CON-RESD-PMD-121719-15-445 A-1 Abboud Diamond Construction, 2. Item #52 Executed BAI, 3. 18-755-A-1 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

December 17, 2019

FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management Division

SUBJECT
Title V
Amendment No. 1 to Construction Contract with Abboud Diamond Construction, Inc. for Onyx Peak Solar Upgrade Project
End

RECOMMENDATION(S)
Recommendation
1. Approve a $521,000 increase in the project budget, from $470,000 to $991,000, for the Onyx Peak Solar Upgrade Project (10.10.0175) located at Onyx Peak, Big Bear (APN 0305-201-05).
2. Approve Amendment No. 1 to Contract No. 15-445 with Diamond Construction, Inc. in the amount of $498,749 increasing the construction contract from $248,729 to a total of $747,478, and extending the contract end date from October 2, 2019 to April 10, 2020 for the Onyx Peak Solar Upgrade Project (10.10.0175) located at Onyx Peak, Big Bear (APN 0305-201-05) (Four Votes required).
3. Authorize the Auditor-Controller/Treasure/Tax Collector to adjust appropriation within the Capital Improvement Program (CIP), as detailed in the Financial Impact Section, transferring $521,000 from the 800 MHz Radio Replacement Project (10.10.0009) to the Onyx Peak Solar Upgrade Project (10.10.0175) increasing the total project budget from $470,000 to $991,000 (Four Votes required).
(Presenter: Terry W. Thompson, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The project budget of $991,000 is comprised of the following components:

Project Design
$40,000
Project Management, Inspection and Testing
$156,398
Construction
$747,478
Construction Contingency
$47,124
Total Project Budget
$991,000

The proposed funding source for the ...

Click here for full text