File #: 2319   
Type: Consent Status: Passed
File created: 6/1/2020 Department: Public Works-Transportation
On agenda: 6/9/2020 Final action: 6/9/2020
Subject: Amendment to Development Mitigation Cooperative Agreement with the City of Redlands for the Alabama Street at Interstate 10 Interchange Improvement Project
Attachments: 1. AGR-PW-Trans 6-9-20 Amend Coop Agr with City of Redlands for Alabama Street @ I-10, 2. COV-PW-Trans 6-9-20 Amend Coop Agr with City of Redlands for Alabama Street @ I-10, 3. MAP-PW-Trans 6-9-20 Amend Coop Agr with City of Redlands for Alabama Street @ I-10, 4. Item #40 Executed BAI, 5. 16-918-A-1 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

June 9, 2020

FROM
BRENDON BIGGS, Interim Director, Department of Public Works - Transportation

SUBJECT
Title
Amendment to Development Mitigation Cooperative Agreement with the City of Redlands for the Alabama Street at Interstate 10 Interchange Improvement Project
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Development Mitigation Cooperative Agreement No. 16-918 with the City of Redlands (City) authorizing the County of San Bernardino (County) to reimburse the City out of the County's Development Impact Fees an additional $964,107 (from $3,712,125 to $4,676,232) for County's cost share of the Alabama Street at Interstate 10 Interchange project in the Redlands area (Project). The Project's total estimated cost is increasing by $4,182,600 (from $10,968,000 to $15,150,600).
(Presenter: Brendon Biggs, Interim Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Pursue County Goals and Objectives by Working with Other Agencies.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The County's share of the Project cost is increasing by $964,107 (from $3,712,125 to $4,676,232), which will be funded by the County's Development Impact Fees (DIF) collected for the Redlands Donut Hole Sphere subarea. The amended estimated total Project cost will be shared as summarized below:

AGENCY
AMOUNT
FUNDING
San Bernardino County Transportation Agency (SBCTA)
$6,717,447
Measure I Valley Freeway Interchange Funds
City
$2,506,921
DIF
County
$4,676,232
DIF
California Department of Transportation (Caltrans)
$1,250,000
Minor B Program
TOTAL
$15,150,600


Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2019-20 Road Operations budget (6650002103 M00012) and will be included in future recommended budgets.

BACK GRO...