File #: 3199   
Type: Consent Status: Passed
File created: 11/5/2020 Department: Preschool Services
On agenda: 11/17/2020 Final action: 11/17/2020
Subject: Capital Improvement Project for Preschool Services Department's Barstow Head Start Site
Attachments: 1. Item #52 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

November 17, 2020

FROM
PHALOS HAIRE, Director, Preschool Services Department
TERRY W. THOMPSON, Director, Real Estate Services Department

SUBJECT
Title
Capital Improvement Project for Preschool Services Department's Barstow Head Start Site
End

RECOMMENDATION(S)
Recommendation
1. Approve Capital Improvement Program Project CIP 21-168 in the amount of $932,985 for the Preschool Services Department (PSD) Barstow Parking Lot Acquisition and Renovations Project (WBSE 10.10.1133), for the acquisition of approximately 1.09 acres of vacant land and construction renovations, located at 1161 West Main Street, Barstow, CA 92311.
2. Approve appropriation and revenue adjustments, as detailed in the Financial Impact Section for the Barstow Parking Lot Acquisition and Renovations Project and authorize the Auditor-Controller/Treasurer/Tax Collector to post necessary adjustments. (Four votes required).
(Presenter: Phalos Haire, Director, 383-2005)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Real Estate Services Department (RESD) will manage the Capital Improvement Program (CIP) project for the Preschool Services Department's (PSD) Barstow site in the total amount of $932,985 (acquisition $200,000, renovations $732,985), funded by the United States Department of Health and Human Services, Administration for Children and Families (ACF). Sufficient appropriation is included in PSD's 2020-21 budget to fund this project. The following adjustments are needed in the 2020-21 CIP budget to establish a budget for this project:

Fund Center
Commitment Item/GL Account
Description
Action
Amount
WBSE
7700003100
54004005
Land
Increase
$932,985
10.10.1133
7...

Click here for full text