San Bernardino header
File #: 7912   
Type: Consent Status: Passed
File created: 4/27/2023 Department: Public Works-Transportation
On agenda: 5/9/2023 Final action: 5/9/2023
Subject: Amendment to Contract with EXP U.S. Services, Inc. to Provide Professional Engineering and Environmental Services for the Phelan Road Widening Project in the Phelan Area
Attachments: 1. CON-PW-Trans 5-9-23 Amend Con with EXP U.S. Services for Phelan Road Widening Project, 2. MAP-PW-Trans 5-9-23 Amend Con with EXP U.S. Services for Phelan Road Widening Project, 3. Item #42 Executed BAI, 4. 21-418 A-1 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

May 9, 2023

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
Amendment to Contract with EXP U.S. Services, Inc. to Provide Professional Engineering and Environmental Services for the Phelan Road Widening Project in the Phelan Area
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Contract No. 21-418 with EXP U.S. Services, Inc., for professional engineering and environmental services for Phase I of the Phelan Road Widening Project in the Phelan area, updating the schedule and extending the contract term for approximately 30 months, for the total term of June 8, 2021 through December 19, 2025, with no change to the total contract amount of $3,503,005.93.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). Phase I of the Phelan Road Widening Project in the Phelan area (Project), Project Approval/Environmental Document (PA/ED), is funded with Measure I Major Local Highway Program (MHLP) Funds administered by San Bernardino County Transportation Authority (SBCTA). On March 24, 2020 (Item No. 35), the Board of Supervisors (Board) approved Project Funding Agreement No. 20-145 with SBCTA to utilize a portion of the Measure "I" 2010-2040 Victor Valley Subarea MLHP funds for the PA/ED phase for the Project. Sufficient appropriation for Phase I is included in the Department of Public Works (Department) 2022-23 Road Operations budget (6650002000 34H15057) and will be included in future recommended budgets.

BACKGROUND INFORMATION
The Project involves the widening of 12.1 miles of Phelan Ro...