Subject: Award Construction Contract to Angeles Contractor, Inc. for the 303 DA Building Sewer System Upgrade Project in San Bernardino
Attachments: 1. CON - PFMD - 05.23.23 - Bid Award - 303 DA Building Sewer System Upgrade - PDA REV6, 2. ATT-Addendum No. 1 - Narrative - 303 DA Building Sewer System Upgrade - .pdf, 3. Item #51 Executed BAI, 4. 23-443 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

May 23, 2023

FROM
DON DAY, Director, Project and Facilities Management Department

SUBJECT
Title
Award Construction Contract to Angeles Contractor, Inc. for the 303 DA Building Sewer System Upgrade Project in San Bernardino
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No.1, to the bid documents dated March 17, 2023, which provided clarification to the contractors' questions in response to contractors' Request for Information, provided revised bid documents, Environmental Maintenance Services Report, and revised the virtual bid opening link, for the 303 DA Building Sewer System Upgrade Project.
2. Award a construction contract to Angeles Contractor, Inc., in the amount of $1,972,000, for a contract period of 290 calendar days, from the date of the issuance of the Notice to Proceed, for the 303 DA Building Sewer System Upgrade Project in San Bernardino.
3. Authorize the Director of Project and Facilities Management Department to order any necessary changes or additions in the work being performed under the contract, for a total not to exceed $111,100 pursuant to Public Contract Code Section 20142.
4. Authorize the Director of Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally Responsible and Business-Like Manner.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item does not require Discretionary General Funding (Net County Cost). The total 303 DA Building Sewer System Upgrade Project in San Bernardino (Project) (WBSE 10.10.1287) budget of $2,677,500 is comprised of the following components:

Description
Amount
Project Design
$168,000
Proj...