Advertise for Competitive Bids for the 800MHz Upgrade Cajon Pass Tower Project in Oak Hills
End
RECOMMENDATION(S)
Recommendation
1. Find that the 800MHz Upgrade Cajon Pass Tower Project located in Oak Hills, is exempt under the California Environmental Quality Act Guidelines, Section 15303 subsection (c), Class 3 New Construction or Conversion of Small Structures.
2. Approve the plans and specifications for the 800MHz Upgrade Cajon Pass Tower Project located in Oak Hills.
3. Authorize the Director of the Project and Facilities Management Department to advertise for competitive bids for the 800MHz Upgrade Cajon Pass Tower Project located in Oak Hills.
4. Direct the Clerk of the Board of Supervisors to file and post the Notice of Exemption of the 800MHz Upgrade Cajon Pass Tower Project as required under the California Environmental Quality Act.
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of the bid documents and the solicitation of competitive bids will not result in the use of additional Discretionary General Funding (Net County Cost). The 800MHz Upgrade Cajon Pass Tower Project (Project) (WBSE 10.10.1011) budget of $1,150,000 is funded from the 800MHz Program Fund (10.10.0009) as approved by the Board of Supervisors (Board) as part of the 2022-23 Capital Improvement Program (CIP) budget.
BACKGROUND INFORMATION
The Project and Facilities Management Department (PFMD) will be able to solicit bids for the United States Forestry leased Project site located at the top of the Cajon Pass, between the north and southbound lanes of the I-15 freeway. The Project will construct a new ...