Subject: Advertise for Competitive Bids for the Fuel Tank Infrastructure Phase III Project
Attachments: 1. ATT-RESD-071321-Fuel Tank Infrastructure Phase III-Victorville Site-NOD, 2. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III-10K-D5 SADDLE CALCS (1), 3. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III-Approved Plans for Bid_04-20-2021_Part1, 4. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III-Approved Plans for Bid_04-20-2021_Part2, 5. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III-Approved Plans for Bid_04-20-2021_Part3, 6. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III--Civil and Structural Specifications, 7. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III-IS-MND Addendum, 8. ATT-RESD-071321-VV Fuel Tank Infrastructure Phase III-StructuralCalculations_TankAndGenerator, 9. ATT-RESD-071321-Fuel Tank Infrastructure Phase III-Victorville Site-Bid Docs-Advertise For Bids, 10. Item #43 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

July 13, 2021

FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management

SUBJECT
Title
Advertise for Competitive Bids for the Fuel Tank Infrastructure Phase III Project
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum to the California Environmental Quality Act Initial Study/Mitigated Negative Declaration for the High Desert Fleet Service Center Fuel Tank Infrastructure Project located at 15000 Tokay Street in Victorville.
2. Approve the plans and specifications and authorize the Assistant Director of the Real Estate Services Department - Project Management to advertise for competitive bids, for the Fuel Tank Infrastructure Phase III Project located at 15000 Tokay Street in Victorville.
3. Direct the Clerk of the Board of Supervisors to re-file and post the Notice of Determination, as required under the California Environmental Quality Act.
(Presenter: Terry W. Thompson, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Fuel Tank Infrastructure Phase III Project (Project) budget of $1,000,000 is funded from the Fleet Management Department (Fleet) Internal Service Fund Retained Earnings as approved by the Board of Supervisors (Board) as part of the 2019-20 Capital Improvement Program (CIP) budget. Sufficient appropriation is included in the 2021-22 CIP budget (WBSE 10.10.0857).

BACKGROUND INFORMATION
Approval of this item will allow the Real Estate Services Department - Project Management (RESD-PM) to solicit for competitive bids for the Project located in Victorville. The Projec...

Click here for full text